Maintenance Notification - Sydney DC - network resiliency improvements

Scheduled Maintenance Report for Squiz

Completed

Dear Customers,

Squiz would like to announce the cancellation of the Scheduled Maintenance Window. Whilst this is important and plans are in place. We feel as a result of Cyclone Alfred impacting the South Pacific now is not the right time to conduct this change.

We will be in touch in due course to announce a new scheduled maintenance window.

Kind Regards
Squiz Customer Support
Posted Mar 11, 2025 - 02:05 AEDT

Scheduled

Dear Customer,

DC team will be working on network resiliency improvements in Sydney Data Centre. We do not expect this to affect production traffic. In unlikely event of a disruption we will have rollback plan in place.

Date: 12/03/2025

Maintenance Window Start: 6pm AEDT

Maintenance Window End: 7pm AEDT

Expected Duration: 1 Hour

Impact: No impact expected.
Posted Feb 26, 2025 - 12:22 AEDT
This scheduled maintenance affected: Squiz Edge.